Liquidated Damages for late delivery shall be 0.5% of the contract price for each week of delay. The claimed amount shall be payable only in case delayed for reasons attribute to ABB.
In all cases, the aggregate amount of Liquidate Damages shall not be exceeded 5% of the total price.