Prepare : Pongpnanot S. KD
Checked : Kriengkrai I. Sup.
Priyakorn C. BM
Approver : Sakchai K. GM
Subject : MMTh-Plant G request monitor and check part tag support Traceability and Preventive wrong packing System (MKD) project.
According KD had project " Traceability and Preventive wrong packing System (MKD) "
that concern Part Tag (MMTh). After checked and found some supplier didn't part tag complete.
So MMTh-Plant G need all supplier follow and monitor our request as below.
1. Attached part tag all supplier package and completed number.
2. Q'Ty part in supplier package same part tag
- Don't manual revise
- If you need change package lot size please feedback to incharge.
3. Paper to print out must use write paper.
*** Target start on 8-Dec-15 ***