To be achieve work purpose together, I will send my team to testing again for the pending an equipments from last inspection, and also we need you (CASIO) supporting for work by safely as following
1) Erection the scaffolding or lift truck for the area of equipments as install height more than your information (8 m.) from our evaluate it's more than 12 m. Krub
2) Issue work permit for working at height (Refer CASIO work procedure)
3) Issue work permit for Electrical work or assign your electrician to be supervisor before work start such as cleaning and testing an equipment in MDB room due to limit for the safety distance
For the inspection date will be inform and confirming you again