-C1 assessed the access date for C5 about the end of year 2015 to early year 2016.
-C1 assessed that they shall finish first stage concrete-westbound from Sanam Chai Station to Hua Lamphong Station which Wat Mangkorn may finish the tunnel alignment before Wangburapha.
-Therefore C1 will arrow C5 to access about early year 2016 (This estimate base on proposed program REV.D (Acc)
C5 informed that the material shall delivery from C4-C2 : Cut&COVER area, CSCBL requested C5 to recheck method statement according to the C5 narrative work Program, Hua Lampong Station are started point.
-C1 requested C5 to check the points of access for pouring the concrete.
-CSCBL requested C1 to updating access date to C5 and requested C5 to prepare the method statement base on schedule of C1 and present in the next meeting.