1) Safety dept. requests to trial sling safety interlock after installation.
2) MMTh will confirm part+skid load to maker on 25 Jul'16
3) Maker will send DWGs to MMTh to approve on 27 Jul'16
4) Fix production start date on 29 Aug'16
5) Maker will prepare construction schedule and send to MMTh to approve on 25 Jul'16
6) MMTh will send exactly skid weight and tolerance to maker on 25 Jul'16
7) Sling Q'ty 4 lines
8) All concerned will confirm all system and safety function on 27 Aug'16 (PE,MT,Body,Safety,Logistic)
9) Testing calculation and result must be submitted to MMTh within Sep'16