SLI and SCI will continue working with EdL to have them issue the sectional taking over certificate, using the Technical folders to push the issue.
Update 2015-05-22: Under review by EdL.
Update 2015-05-29: Follow-ups are continuing. EdL continues to review. In the meantime, the TOC preparation for other completed work is continuing. Enova must coordinate with SLI to ensure all documentation is received according to the TOC submission plan.
Update 2015-06-19: GNK is back from China today and will review.
Update 2015-07-03: GNK requested to have a progress table for all VTE installation works completed and still under construction.