According Symphony is required to cut over the signal from the fiber optic network for avoiding construction work at The Immigration Office of Mae Sot. So we have plan for working on September 24, 2015 at 3 am – 4 am in order to preventing the effect maybe occurred, please kindly note.
If possible, we will cut over the fiber optic network of MPT into the cable that we have installed on the friendship bridge of Thai – Myanmar. So we would like to know that MPT will agree with our schedule plan or not?
We look forward to hearing from you and don’t hesitate to contact us.