As K.Chartchai inform this morning, UTCT want to finish select contractor in Jan 16 and want to start project Feb 16. Then the consulting, we need to hire in Jan 16 also for take care selection, material will use and supervision. Please find quotation of consultant fee in attached file.
Tentative repair schedule below was recommended :-
1. Finalize the repair cost comparison and select vendor not later than end January , 16.
2. Commence wharf repair by February , 16.
So far we have received just one quotation from SCB which please get another two quotations from other construction companies. We are flexible to get the quotation from medium or small company who has experience to repair wharf.
For consultant fee : In addition to the consultant fee quotation from Dr. Thanakorn , it will be good if you also can get the quotation from other two consultants for cost comparison.
I think, I can’t find other consultant. May you advise or ask somebody to takecare.
In part of contractors, I will retalk to contractors and inform result you back.
As K.Chartchai inform this morning, UTCT want to finish select contractor in Jan 16 and want to start project Feb 16. Then the consulting, we need to hire in Jan 16 also for take care selection, material will use and supervision. Please find quotation of consultant fee in attached file.Tentative repair schedule below was recommended :-1. Finalize the repair cost comparison and select vendor not later than end January , 16.2. Commence wharf repair by February , 16.So far we have received just one quotation from SCB which please get another two quotations from other construction companies. We are flexible to get the quotation from medium or small company who has experience to repair wharf.For consultant fee : In addition to the consultant fee quotation from Dr. Thanakorn , it will be good if you also can get the quotation from other two consultants for cost comparison.I think, I can’t find other consultant. May you advise or ask somebody to takecare.In part of contractors, I will retalk to contractors and inform result you back.