AREAS OF CONCERNS/ SPECIAL ATTENTION
At the first two month of the EPC Project, insufficient resources were mobilized to the project. This caused delay in engineering phase of the project. Contractor recovery of this delay is ongoing.
Resource mobilization for this package is not as per EPC Contractor plan. Only one construction team has been mobilized comparing to four (4) construction team planned. This issue has been highlighted to the Contractor’s PMT during monthly progress meeting.
Contractor tends to deviate from the approved procedures without receiving official approval from PTT/TET. This issue has been highlighted to Contractor’s PMT team.
Based on current status of the Contractor’s progress, two month delay in achieving second milestone of the project is envisaged.