Dear Compose team and All AAE PM , E&I team concern.
Now is serious situation of AAE with electrical work.
Update on 8 Oct 15 : 1.00 pm.
As below detail is update follow actual condition (I list by priority
sequence of require).
1. PTT LNG
1.1 Local panel : 4 sets
--> Delivery panel to AAE on : Sun 11 Oct 15.
--> Internal FAT with AAE on : 10-12 Oct 15 with report by Compose.
--> Delivery to site on : 13 Oct 15.
Note : This panel issued about color code mistake by compose so AAE request
compose repair to closed follow schedule too and can parallel wiring.
1.2 Safety switch panel : 2 sets
--> Delivery panel to AAE on : Sun 11 Oct 15.
--> Internal FAT with AAE on 10-12 Oct 15 with report by Compose.
--> Delivery to site on : 13 Oct 15.
Note : This panel we can see only panel that no have equipment's inside?
1.3 HVAC panel for GIS(Relay panel) request modify addition concept
converter analog signal : 1 set
--> Delivery panel to AAE on : Sun 11 Oct 15.
--> Internal FAT with AAE on : 12-13 Oct 15 with report by Compose.
--> FAT with POSCO & PTT LNG on : 14 Oct 15.
--> Delivery to site on : 15 Oct 15.
1.4 Local panel SS for Existing CCR : 1set
--> Delivery panel to AAE on : Sun 11 Oct 15.
--> Internal FAT with AAE on : 12 Oct 15 with report by Compose.
--> Delivery to site on : 13 Oct 15.
1.5 Instrument box : 2 sets
--> Delivery panel to AAE on : Sun 11 Oct 15.
--> Internal FAT with AAE on : 12 Oct 15 with report by Compose.
--> Delivery to site on : 13 Oct 15.
Note : This information I informed and committed to POSCO PM (Mr.Lee @
office on 7 Oct 15).
So now this situation is very tight for AAE and compose about electrical
work.
Please share information with real time in case of accident or other for we
support clarify.
As below is internal punch and require from AAE.
I hope to both party of AAE & compose must be keep schedule follow
require.
Sincerely yours
Harin B.
Harin Bolwisej.