Following Monday’s site construction meeting:
1. Weapons out of Building 4 and Building 5 - 2pm 5th November.
2. Weapons accept of Building 1 and Building 2 on the 8th November.
3. Weapons do not remove shower stones on Building 1 Art until after November 20 - but complete: mirrors, electrical, sinks, taps, (stone polish by others) by Midday 19th November. The only item remaining works after November 20 is the shower stone removal an installation minor decorations.
4. I have asked KS to supply Building 2 Art Shower Stones first ahead of Building 1 (due to item 3) - please co-ordinate with Nat (above) [NAT]
5. IF you can achieve program for Building 1 (leaving shower stones) then this enable Hotel to give you Building 3 on 12th November.
6. Please quickly measure and send to KS:
- Building 3 shower stones
- Villa [ART] 701, 702 and 703 shower stones (both main bedroom and second room)
- Villa 706, 707 and 706 (second room)
- Villas to have NO pattern on the granite.
While we are permitting guest use of Building 4 and Building 5 (and potentially Building 6 on 12th November) we need to make it very clear it is NOT a contractural handover or acceptance. We will work with the Hotel to regain access to complete all incomplete works and defects and inspections for a formal and contractural handover. Right now we are both compromising to enable provision of work areas ahead of you.