For this order we have lead time for wire making from supplier about 2 days and you have to prepare fine silver and 2,000 THB labor cost for them
So may we can get the wire on 15 July mean we will finish this order on 21 July,
If you need to ship on 17 July we have to do parallel way by make some wire by our self about 1,000 g. and start run before the wire come from supplier
Please advise for you direction , postpone shipment or make some wire in house