Dear K.Ya,
Please help to pass on the following information to the ECT Production Team, notably Nazeri as soon as possible. Your support & cooperation will be very much appreciated.
"Everyone do not wish to experience again the same bad casting results after the Songkran Festival, when ECT had a long stretch of holidays. To be free from all these, I am listing down the important aspects for the ECT Production Team to carry out & I'm very sure the team members are well aware of those things.
1) Maintain the consistency in terms of density & thixotropy of the casting slip in all the agitating tanks, before the closure.
2) Have someone on standby and daily periodic checkings on the continuous agitation of the tanks with casting slip. Any power failures or any interruptions on the agitation of the tanks should be rectified immediately.
3) 2 days before the start of production, have someone to check the density & thixotropy of the casting slip and whatever that is not right, should be adjusted.
4) Check again 1 day before the start of production & of course on the morning of production to ensure all parameters are maintained.