Dear K Burin,
Apologies for the delay due to an internal miscommunication. I checked with my team and the payment is released and ready for pick-up any time tomorrow.
Regarding the PV module importation: this is not at all related to any failure on our side and entirely due to the delay of the project progress. We continue to proceed with all customs, VAT and similar payments in a timely manner as per the information provided to us. Lot 2 was released and will arrive on site in a few days--before lot 1 was installed.
I do not appreciate any indication of delay on our part on this account given that Irradiance delivery of mounting structure is more than one month behind schedule on a 4 month project!