Any standard or code of practice referred to in the Contract or any other standard or code of
practice that may be substituted therefore shall be the latest edition. All relevant particulars
and conditions in any standard or code of practice referred to in the Contract relating to
material, quality and workmanship shall be complied with and all tests specified shall be
conformed to.
2.3.7. Where any standard or code of practice is referred to in the Contract, other appropriate
national or international equivalents may be substituted subject to the approval of the
Engineer as described in Clause 3.0 hereof. Where other appropriate national or
international standards are offered the Contractor shall submit to the Engineer for approval a
copy of the alternative standard or code of practice in English and shall provide such further
information as is required to enable the Contractor to demonstrate to the Engineer that the
alternative national or international equivalent may be substituted.