5. Electric Details
a. Is electricity both exported from and imported to the site?
i. For both power sales and purchases, please describe the contractual details for each, as applicable.
ii. What alternatives or options exist for power purchase (e.g. alternative suppliers, different tariffs, etc?)
iii. Does the price depend on the time of the day, season of the year, or similar factors?
iv. Average price and amount purchased/sold in the last year.
b. What is the normal total power requirement for the site?
i. How much power is normally generated internally?
ii. How much power is typically imported or exported?
iii. What is the usual scenario regarding power import or export and, if applicable, how often does it change?
c. Please, list any significant electric system constraints, such as transformer limitations, etc.