Dear All supplier
As we have discussed on 25/3/15 at PB tech (office) about the Project Dismantle and installation PET line 1 from Thainamthip Pathumthani plant to vientiane, Laos.
I would like you send me the proposal as list below.
Scope of work.
1 Dismantle Thainamthip (How many days?)
- Mechanical technician (How many people)
- Electrical technician (How many people)
- Tools and consumable
2 Packing Thainamthip (How many days)
- Packing list
3 Loading Thainamthip (How many days)
- Heavy tools
4 Transportation From Thainamthip to Vientiane, Laos. (How many days)
- Export duty
- All document about shipping
5 Unloading Coca – Cola Vientiane, Laos (How many days)
Unpacking
Positioning
Installation
- Mechanical technician (How many people)
- Electrical technician (How many people)
- Heavy tools
- Tools and consumable