On 8th September 2014 have heavy rains found the water leaks through pee-cast wall many points refer from PPS, PISA and ITD meeting according attach file (1) PISA could not deny that water leak are not from façade work.
Therefore, we instruct you to immediately increase you resources and to accelerate fixing the water leak. We are give thanks for your assistant before however, please kindly to fixing until the water stop ingress to show that you have already revise.