Dear sir,
Swadee Krub Hier Thuanchai Tee Kid Thueng
Due to delay of total Maintenance Nam Mang3 Unit1 works
I have trouble and obstacle manners in the managing of Nam Mang3 Unit1 Major Overhaul maintenance Project , that were substituted participant to U-services in the topic of :-
1. Schedule for Start and Finish due date centering and alignment activity.?
2. Finished and on site date of New parts of all Guide bearings and thrust bearings.?
3. Schedule that are an able to drive all activity continue until through finish activity.?
Especially critrical parts : Schedule through finish and on site date of Main Inlet Valves 2 SE. Their are most effective for overall works.
Interpolate Work that are may be confirm to related party is " PM Control works" from singapore . And we "VASE" me be confirm schedule backward to PM control next.
There for , please confirm by accuracy currently schedule to me, and Mr.Keowudone, Mr.Manmeang. Mrs. Sompong in urgently .