Tan Son Nhat Airport project which we already provided elevator and escalator in 2015. Now, it is expanding one terminal. There are 3 elevators and 4 escalators for this phase. The client requests to provide the same specification with the existing one. There are some changings of our product, we will negotiate with client, however, the post of escalator, it should be same as the existing one.
Regarding to the existing post, please kindly find the attached for detail and the order no of escalator and post is “VN05161/HCM-T” (The post is from MELINA)
Please kindly advice for above matter, please kindly find the attached specification for more information.
In addition, we have sent T/I: T-VME-14-A0294 to check some special points.