6.5 Should the Customer not punctually take over products announced as being ready for dispatch, rommelag ag is entitled to
demand payment of the order price and to store the products at the Customer’s risk and expense, whereby rommelag ag
shall be entitled to claim liquidated damages for warehousing costs up to a maximum of 0,25 per cent for each full week of
the delay; however, they shall not exceed 5 per cent in all, calculated on the basis of the net price ex-works of the delayed
talking over of the products (or portion thereof).