liquidated damages are a genuine pre-agreed estimate of the likely consequences and are understood to be the sole remedy for the respective shortfall in performance. 
liquidated damages are expressed as a percentage of the contract price for the concerned
functional unit less the contract price for options, exchange parts and advisory services relating thereto.
the maximum amount of liquidated damages for non-achievement of performance parameters shall not exceed 5% of the contract price of the respective concerned functional unit.