Today is LR final meeting with Devan lay, so after it UK will star working with all comments/modifications agreed to updated SRF for LA or SMS samples
As marketing Samples ETD is March 14, to save time and start working asap, we have agreed with UK to receive SRFs information divided in 3 lots.
For Vietnam & China, will resume working after CNY/TET so 1only one week before download, but for Thai & Indo can follow below schedule
1st Lot: after Devanlay meeting – Feb 5th.
• It is schedule to receive first feedback after Devanlay meeting on Feb 5th, but we will only receive information of SRFs that will remain same as LR samples.
• To provide the info, UK will use AW16 Marketing Sample Tracker. You just need to check the column Change style Y/N, and you will only proceed with No change styles (N).
• As this SRFs will remain same as LR samples, no need to download SRFs at this stage, just do in on Feb 22.
• Still is not clear if Tracker will be shared by share point of just sent by email