Engineering Department– Already reviewed the HVAC’s drawing and the BOM (Bill of Materials) is update into system. Process flow chart, routing and work instruction will be ready for pilot run at Engineering trial out line on May 2nd week. Can release and implement to production on May 3rd week to June 2nd week.;