Dear Prachayavut,
It was nice meeting you yesterday at site yesterday.
As informed by K. Chaiwat, please note that the handover of the shafts in both buildings could earlier than what was informed in trailing emails: back building could be around 20th July 2016 and front building around 5th August 2016. K. However, he has to discuss with PLE for actual lift shafts’ completion schedule and will update you soon. Please prepare for your installation teams accordingly.
For all your requirement, please communicate & coordinate with CM, K. Chaiwat.
Please urgently provide following:
- Dumbwaiter shop drawings & installation schedule,
- shop drawings for lift call panel, hall lantern etc., and
- elevators’ installation schedule
- list of items that are not in your contract but are required for the completion of elevators, dumbwaiters and their full functioning & handing over.
Hope to hear from you soon. Thanks.