We are still talking with Hoko on this inquiry. I think the validity has already expired.
But could you plz extend validity until Oct 25th ?
Actually, Hoko has a very positive attitude for the order however we faced strong price negotiation from them…
Komatsu-san will advise you for the price matter. Plz wait a while.
Meanwhile, I’d like to check lead time of this order.
Plz advise how many days you will require for the production, packing(Label, carton) after our order.
For the packing material, there is a possibility to change current label and carton design from this order.
So plz let us know the lead time if we ask you to change both packing material design as well.
PIC of Hoko mentioned that they would like to receive this container by end Nov as a target.
Thank you.