The following list is out of scope activities which exclude in project AFE and project master plan. Time and cost impact to be considered.
• SimOps with other projects & Operation
• Waiting for Weather (WOW) more than 12 days
• Partial team (less than 10 POB- FE Con) during construction
• Work break-in (demobilization and resume)
• Travel time more than 5.5 hours per day.