Figure 6-1 illustrates the severe state of internal variation my
study team found affected one factory (a result that does not seem
to be atypical in this industry). The chart depicts its problem: substantial
cycle time variation—wide swings in the time it took to
build each successive unit, deviating as much as 30 percent from
the average.