If a Subcontractor’s obligations extend beyond the expiry date of the relevant Defects
Notification Period and the Engineer, prior to this date, instructs the Contractor to
assign the benefit of such obligations to the Employer, then the Contractor shall do
so. Unless otherwise stated in the assignment, the Contractor shall have no liability to
the Employer for the work carried out by the Subcontractor after the assignment takes
effect.