Obligations of the parties
Article3: The obligations of the party “A” is to assure to provide and make payment the finance to the above project to meet the requirement as entered into this agreement
Article 4: Obligations of the party “B”
4.1: To settle the impacts of the Country Road construction project implementation
4.2: The party “B” shall provide the documentations related to the project as approved by the Royal Government for the Country Road construction project implementation
4.3: The party “B” is to insure, coordinate the public administrative affairs to the party “C” during the construction project implementation period
4.4: The party “B” shall give the convenience to the site with the construction plants such as soil, stone, laterite, cement, steel and bitumen to the party “C”
4.5: The party “B” shall be responsible to the party “C” to import the machinery for implementing the construction project of the Country Road construction project without paying the import tariff (duty free 100 percents)