According customer suzuki have adjust produciton plan in March 2015 now we face data in system
it difference with actual PO. this is very difficult and confuse for production plan so this issued I have
reqeust to Suzuki share to us part by part and produciton per day of March 2015
Please check more detail attached file.
In attached file are SMT’s Production Plan (actual production )
We try to produce about 4,702 unit within MAR-15 ,also we do over time every day (Mon-Fri = 10 Hrs & we do every SAT(= 11 Hrs)
YP5 = 923 unit ( average 38-44 )
YLA = 3,781 unit ( average 146-160 )