3. First roll bundles will be put against inner container wall.
4. The lowest bundles will put directly on the container floor
5. Skid (t15x120 mm) 3 pcs will be put freely on top of the lower bundles along the 8' side. The skid must be little shorter than board (not same length)
6. Fill up space between bundles and container wall with air bags
7. Protect last bundles with 2 of w40-50 mm belt crossing.
8. Recommend not to use plastic warping to prevent water condensation in some season. By theory, if your board MC is about 6-7 it will not absorb much MC in the air that will cause warping. But if your board MC is lower (after seasoning) that is problem.