The time schedule, Annex II is based on the provision, that the down payment will be received by DÜRR within 15 days from date of contract, and the operative L/C will be advised by an international bank to DÜRR within 3 weeks from date of contract. Delays longer than 1 week from the agreed dates, stipulated in Article 5, will cause revision of the time schedule and penalty dates.