It is expressly understood that breakdowns of Constructional Plant on land or at offshore location during the performance of Work shall not be regarded as physical conditions which would not have reasonably been foreseen by Contractor and as such, the cost of such breakdowns and any resultant delays and costs thereof shall be to Contractor's account.