5.2.3 Instrument wiring, along with instrument mounting and installation, shall be in accordance with project specification.
5.2.4 Instrument installation shall be tropic proofed in accordance with project specification.
5.2.5 Check the accessibility, operability and maintenance-ability of each instrument.
5.2.6 Verify that instrument is not subject to excessive vibration.
5.2.7 Verify that instrument locations are not obstructing traffic and passage.
5.2.8 Check the slope of pressure lead pipe and sampling pipe.
5.2.9 Check the high and low pressure connection of instrument lead pipe and sampling point.
5.2.10 Verify that the lead pipe support are firmly fixed.
5.2.11 Material is in accordance with specifications.
5.2.12 Instrument vents and drains are in accordance with piping drawings.
5.2.13 Position, routing, supporting and tag numbering of tubing in accordance