The original ITP was received from PM SILALERT, it was not created by PAE and then our QA/QC department reviewed and revised it and submitted to PTTEP. I was surprised why it was commented a lot. However it was necessary to finalize to continue our construction.
Please note that K. Warajak do not pass the probation, so he will finish his trying period end of May,2014. It cannot expect his output. Our construction schedule shall go on, so it is necessary to be reviewed and revised by helping together. Otherwise ITP cannot be finalized.
Please provide your original one again, I want to review what happen on the ITP and I will try to finalize the ITP problem.