GM Supplier ASN 0 Compliance ANNOUNCEMENT
FCL ( Normal FCL, DHL to deliver the container to supplier’s plant and supplier stuff the cargos into the container by your own facility)
Booking Cut- off time: Friday Week A-1
Pick-up Cut- off time: Friday Week A
Sailing day: Monday Week B
*Week A= DELJIT Week*
*Week A-1 = One Week before DELJIT Week*
Pls note as it is a pre-booking process, so once you receive DELJIT on Monday and Tuesday, pls refresh your booking(SRF) and documentation with the correct part number and QTY.
The complete SRF(shipping request form) + Packing list are mandatory requested once booking sent by the supplier. As per the supplier welcome package: Documentation (invoice + packing list) is requested sent together with SRF by the supplier or no later than pick-up date as the bottom line
SRF Timeline
GM Supplier SRF Compliance Instruction / DHL-AP Regional Control Tower / AP>SA Team / V1.0 / May 2016