Tasks Take Less than a Day (+)
Throwing hour estimations out the window was liberating for the teams and
managers. Stories are assigned a degree of “difficulty” in story points and tasks are
simply items that are binary – either done or not done. A task is always less than a
day, so if a person is working on a task for more than a day, we know they’re
probably impeded.