As PISA request to open partition wall in stores room at the back of Room shop, level 4th to find the cause for the water leak inside the shop and the shop want to know that which contractor who will come to open and close after finish fixing. We inform that we will administer as memorandum above. As process and responsibility as below;
1. ITD will open the partition gap about 60x60 cm. at levels above the shelf that PISA suggested position. Therefore, the shop moving their stuffs on the shelf before ITD starts working. If PISA wants to open more, please inform the shop for permission to proceed.
2. After we complete working ITD will close the gap of partition wall and painting.
3. The shop will move their stuff by their own and if ITD works damage their goods, we will pay for the damage cost as per actual cost.