Inform to supplier to revised BL on 5 Jan 2015.
From Kan-sanei Thailand to Sanei engineering
Revised BL delay this shipment arrive seaport on 6 Jan 2015 but we receive the BL complete from supplier on 8/1/2015 after ship arrived sea port . The Liner submit first data of Kan-sanei Thailand for manifest to customs we must declare to customs for name shipper is Sanei engineering . We can do customs clearance delivery to MTA on 17/1/2015 that postpone plan first delivery from 12 Jan 2015 to 17 Jan 2015.
The shipment delay 6 day. We pay cost increase for container storage is 3,750 THB and Demurrage chg. Is 2,600 THB
1 Container 40 ‘F 250 THB 6 day = 1,500-
1 Container 40 ‘H 375 THB 6 Day = 2,250-
This cost for tatal cost charge to supplier 6,350 THB