4.1 Location structure position by surveyor.
Survey mark alignment .
4.2 Setting of leveling and Installation.
Check dimension and elevation of steel plate should be conform with approved shop dwg.
Check dimension of structure shall be convenient and proper before grouting
Preparation rough surface of structure and marking finish level of installation
Cleaning before installation.
After completed installation work process, top plate surface must be smooth,
straight and free from cracked and dent to required elevation as.
Seting time of epoey work after complete 24 hrs.
Curing time of epoey max loand after complate 78 hrs.
4.3 After complete 1 hrs. Survey re-check alignment of location.
4.4 Required alignment working area and elevation conform with for construction drawing.