Case II: New VC1 is overlapped with Existing VC1
• Operation Date = 10/5/2013
• The existing VC1 of 1.2 is set for period 1/5/2013 – 31/12/2049
• The new VC1 = 1.5
As Period of new VC1 is overlapped with existing VC1 so, system needs to adjust period as following;
The end date of existing VC1 is shorten to be the operation date.
The new VC1 is generated with entering start date is operation date + 1 and end date as ‘31/12/2049’.