• Now the land location has been unlocked by retail regulation; therefore, we have a window opportunity for retail area without restriction of retail regulation.
• Respectively, we noticed that during the time that the Notification of Town Plan Department is expired and the new Notification of Interior Ministry is starting enforcement, it takes approximately about 5-6 months. So, we should speed up for granting construction permit prior the new retail regulation will come effective.
• The besides of project land is adjacent to Prasat School. According to the Ministerial Regulation of Ministry of Finance B.E. 2548 prohibits for selling retail liquors type 3. So PA should negotiate with landowner to separate land title deed between project land and Prasat School in order that TL claims the project land is not adjacent to Prasat School for selling retail liquors.