Dear All,
We do apologize for our mistake for the date (As red marked in earlier mail) and also needs update some revise as follows
Tuesday 29th:
- All chemicals has been purchased and goods will be on site on coming Thursday 1st.
-Waste transportation, waste tank and waste disposal is under cooperation.
Wednesday 30th:
- Under preparing all relates document and will be submitted to PTT by today.
Thursday 1st:
- Site survey and connecting preparation.(In the morning half)
- Kick off meeting with Kanken & PTT (Tentative in afternoon).
- Facilities mobilization and inspection.
Fridays 2nd:
- Safety training and 1st day operation.
Saturday 3rd:
- 2nd day operation.
Sunday 4th:
- Last day operation may continue in morning half.
- Housekeeping and mobilization will be done in afternoon.