3. Hydrological Observation Work Progress:
a) On 28 - 30 Apr’14, CRCCI finished site reconnaissance, seabed sediment sampling, tide, wave
and inshore flow regime observation on the north bank of proposed port area along the Macuse
and sand tracing observation and inflow regime.
b) On-Site Hydrological Observation work has been in progress in full scale to collect and compile
data of Hydrologic Observation such as Tidal Elevation, Current and Turbidity, Seabed
Sediment Sampler etc.
c) Hydrological Observation Progress as below;