• The Zone 2 Plaza Works started 15 SEP 2016 and targeted to be completed by 10 NOV 2016. I informed Niran how the works are affected by the ongoing rain and Times provided two 30 meter tents to keep progressing their works and are working nights when weather permits. Niran requested to ask Times if they can provide bigger tents, Times informed me that those are what they have on hand but I’ll ask again to confirm.