Dear Som-san & VD00 Team,
Please be updated VD00 next co-check schedule would be arranged on or about the Beginning of August/16. More actual date will confirmed you again later soon.
This Time Kick-Off VD00 Parts subjective for :
-A2-Group : Local Parts (RHD) / Event PPT#1
Requesting 3 P/Nos. as below :
1) 8974666990 MAT KIT;FLOOR Qty 2’U Del. on
22/09/16 to G/W Plant
2) 8974667011 MAT ASM;FLR K/UP Qty 1’U Del. on
22/09/16 to G/W Plant
*3) 8974670101 MAT ASM;FLR K/UP Qty 1’U Del. on
22/09/16 to G/W Plant
Note :
>> P/No.1 & 2 had been checked and approval before, so this time just
co-check only new P/No. in No.3.
About Co-Check part qty will be firm again whether only 1'u or more (Isuzu's standard for Trial Part Approval is @5'u at least).
Any updated infos. will inform you again asap.
Thank you & Best Rgds,
Siranee J.
Asst. Mgr. Sales & Marketing
*************************************
Meiwa Industry (Thailand) Co.,Ltd.
62 Thaniya Building, 11th Floor, Room 1103, Silom Road, Suriyawong, Bangrak, Bangkok 10500 Thailand
Tel : 02-632-8255
Fax : 02-632-8256
Mobile : 063-139-5109
E-mail : siranee@meiwaindustry.co.th
-----Original Message-----
From: siranee [mailto:siranee@meiwaindustry.co.th]
Sent: Tuesday, July 05, 2016 2:00 PM
To: manatsawee@meiwaindustry.co.th; 'khajornsak'
Cc: chareeya@meiwaindustry.co.th; kanlaya@meiwaindustry.co.th; juthamas
(juthamas@meiwaindustry.co.th) ; nucharee@meiwaindustry.co.th; 常樂 健 (t-jyoraku@meiwasangyo.co.jp) ; 福澤 陽平 (y-fukuzawa@meiwasangyo.co.jp) ; '石田 光二' ; nucharee@meiwaindustry.co.th; 'anothai@meiwaindustry.co.th'
Subject: RE: VD00 A2 Group : Kick-Off New Part for MWTH req Co-Check & Delivery Plan
Dear All VD00 MWTH Project Team,
Herewith an attached New Updated VD00 A2-Group Master Schedule received from IGCE today.
Pls kind refer their upadted schedule plan as in attached file.
Data received today 2016-Jul-05.
Note : Today received schedule almost all same with the latest received one.
Thank you & Best Rgds,
Siranee J.