Logically, the extension from a minimal to a maximal time-lag also holds
for start-start, finish-finish and start-finish precedence relations. The precedence
relations can, and often will be used in combination, as shown in an illustrative
project network of Fig. 2.9. The numbers above each node denote the activity
durations and the labels associated with the arcs refer to the generalized precedence
relations.