13. Inspection Data Requirements
The supplier shall prepare an inspection data for quality assurance.
(Recommend use attachment B-7: Initial Sample Parts Inspection Report)
13.1 The supplier shall submit inspection data at each delivery of Pilot Production, the first
shipment of Volume Production and also the first shipment of Design Change and
Process Change during Volume Production stage.
13.2 Number of products to be inspected
13.2.1 At least 1 piece (vehicle parts) or 3 pieces (engine parts) per cavity, tool or mold
etc, Inspect all points which shown on drawing.
13.2.2 At least 5 pieces per cavity, tool or mold etc, Inspect all points which shown in
Inspection Standard.
13.3 The supplier shall attach the inspection data into the palette with the measured product
and also send it by fax or e-mail to ISUZU Quality Control Department.
13.4 Also identification for inspected parts shall be added.
13.5 Supplier shall retain inspection data of each lot of products shipped.