Dear all
Per our latest meeting ,pls find the below minute of meeting ;
1. Development team confirmation the Helium gas station for support 2 cylinders.
2. There is more additional request as following ;
2.1 Change machine working area from 850 x 1220 mm. to be 1000 x 1000 mm.
2.2 Helium gas station that 2 locations for proposed layout in the proposal package by need to make pipe line to connect between lab C/R and Helium cylinder.
Option 1 : Inside lab C/R reduce space by main building need to drop concrete wall and lift up installation.
Option 2 : Outside lab C/R by on the side of road the proposed location is nearby ramp & emergency exit.
3. Pending utility requirement data from Development team.